# Department of War Suspends the November CMMC Phase 2 Transition

## What happened

On 3 September 2026 the Department of War signed [Class Deviation 2026-O0025, Revision 3](https://www.acq.osd.mil/dpap/dars/classdev/DFARS_RFO/Part-240/2026-O0025_Rev3_TAB_A_Deviation_Memo.pdf). It tells contracting officers to work with requiring activities to remove or revise Cybersecurity Maturity Model Certification (CMMC) requirements in new and existing solicitations and contracts. It applies a Chief Information Officer memorandum of 13 July 2026, which, the deviation says, suspends the November 2026 CMMC Phase 2 transition.

## What it changes

Requiring activities may include CMMC Level 1 (Self) or Level 2 (Self) assessments in all procurement requests. Baseline compliance with NIST SP 800-171 Rev 2 under DFARS 252.204-7012 stays required.

Active solicitations get amended as soon as practicable. Existing contracts lose the requirements by modification before the next option period, or through the next scheduled administrative modification. The deviation remains in effect until rescinded or incorporated into the FAR, DFARS and DFARS PGI.

The rule text itself has not moved: [the eCFR](https://www.ecfr.gov/api/versioner/v1/versions/title-32.json?part=170) lists no version of 32 CFR part 170 after 16 December 2024. The change works through contract terms. We rely on the deviation for the content of the memorandum, because we could not open the memorandum itself.

## Who is affected

Contractors and subcontractors bidding for or holding Department of War contracts with CMMC requirements. The deviation sets no limit by company size.

## What to do now

- Check your open bids and contracts for CMMC clauses, and ask your contracting officer how and when they will change.
- Keep your Level 1 or Level 2 self-assessment current. Those requirements can still appear in procurement requests.
- Keep working to NIST SP 800-171 Rev 2. The suspension does not remove DFARS 252.204-7012.
- Decide what to do with any planned third-party assessment and record why, since the deviation can be rescinded.

Principal Consultant

## [Ahmet Ucar](https://grc.plus/consultant/ahmet-ucar/)

Helps clients comply with their regulatory requirements with a plan their board can approve.

[Book a 30-Minute Call](https://meetings-eu1.hubspot.com/ahmet-ucar)