FERC Approves Virtualisation CIP Standards and CIP-003-11 for Low Impact Systems

FERCFederal Energy Regulatory Commission Orders 918 and 919, effective 26 May 2026, approve 11 CIPCritical Infrastructure Protection standards for virtualisation and CIP-003-11 for low impact BES Cyber SystemsOne or more BES Cyber Assets logically grouped by a responsible entity to perform one or more reliability tasks for a functional entity. The NERC CIP standards apply their security requirements to BES Cyber Systems that support the Bulk Electric System.. NERCNorth American Electric Reliability Corporation must build a programme with criteria and reporting for the per system capability exception.

24 March 2026 · Adopted

What happened

On 24 March 2026 the Federal Register published two FERCFederal Energy Regulatory Commission final actions, both effective 26 May 2026.

Order No. 919 (Docket RM24-8-000) approves 11 modified Critical Infrastructure ProtectionThe group of NERC Reliability Standards that set cybersecurity and physical security requirements for the North American bulk electric system. CIP standards are adopted by the NERC Board and approved by governmental authorities, which makes them mandatory for the entities they apply to. (CIPCritical Infrastructure Protection) Reliability Standards, plus four new and 18 modified NERCNorth American Electric Reliability Corporation Glossary definitions, including Cyber System, Management Interface, Shared Cyber Infrastructure and Virtual Cyber Asset.

Order No. 918 (Docket RM25-8-000) approves CIP-003-11 to reduce the risk of a coordinated attack through distributed low impact BES Cyber SystemsOne or more BES Cyber Assets logically grouped by a responsible entity to perform one or more reliability tasks for a functional entity. The NERC CIP standards apply their security requirements to BES Cyber Systems that support the Bulk Electric System..

What it changes

CIP-003-11 adds controls to authenticate remote users, protect authentication information in transit and detect malicious communications at assets with low impact BES Cyber SystemsOne or more BES Cyber Assets logically grouped by a responsible entity to perform one or more reliability tasks for a functional entity. The NERC CIP standards apply their security requirements to BES Cyber Systems that support the Bulk Electric System. and external routable connectivity.

For the virtualisation standards, NERCNorth American Electric Reliability Corporation‘s approved plan sets the effective date at the later of 1 April 2026 or the first day of the first calendar quarter 24 months after the applicable order takes effect. Entities may adopt early at six, 12 or 18 months. We read Order 919 for this plan, not NERCNorth American Electric Reliability Corporation‘s plan documents. We did not read the separate plan for CIP-003-11.

FERCFederal Energy Regulatory Commission also directed NERCNorth American Electric Reliability Corporation to build a programme for the “per system capability” exception: clear criteria and documentation, mandatory reporting by entities that use it, and an annual anonymised report to FERCFederal Energy Regulatory Commission.

Who is affected

Responsible entities under the NERCNorth American Electric Reliability Corporation CIPCritical Infrastructure Protection standards in the United States, including those with low impact BES Cyber SystemsOne or more BES Cyber Assets logically grouped by a responsible entity to perform one or more reliability tasks for a functional entity. The NERC CIP standards apply their security requirements to BES Cyber Systems that support the Bulk Electric System..

What to do now

  • List assets with low impact BES Cyber SystemsOne or more BES Cyber Assets logically grouped by a responsible entity to perform one or more reliability tasks for a functional entity. The NERC CIP standards apply their security requirements to BES Cyber Systems that support the Bulk Electric System. and external routable connectivity, and check them against the three new CIP-003-11 controls.
  • Decide whether to adopt the virtualisation standards early, and tell your Regional Entity if so.
  • Record every place you rely on “per system capability”, with the alternative mitigation, ahead of NERCNorth American Electric Reliability Corporation‘s criteria.
  • Confirm your compliance dates in NERCNorth American Electric Reliability Corporation‘s implementation plans.

Get updates for the United States

One email a week when something changes. Add other countries if you need them.

Countries
United States

Pick one or more

One email a week, only when something changed. Each email has an unsubscribe link. Privacy notice

RSS Feed for United States

Loading the form…